Got it sprayed today . 2" closed cell under the subfloor and 4-5" open on ceiling and walls.
Also ran the wire from meter box through wall into panel.
Water , electric and septic all should be going in next week.
Got the pex all studded out. Ran 1/2" through house and connected to 3/4" which will be main line.
Hoping to knock out the pvc drain lines this weekend.
Mounted outside units for mini splits.
Material for ceiling and walls being delivered tomorrow. Gonna do corrugated tin ceiling throughout. Drywall in bed and bathrooms , and ceder picket walls in living .
LifeProof waterproof flooring being delivered mid week.
Keep forgetting to take pics of everything.
Sent from my SM-G970U1 using Tapatalk
Comment
-
Comment
-
-
Moving slower now that I'm back to work. Had some help out there today. ( Thanks Trevor) .
Got a little drywall started. Got the ceiling started. Mounted outside units, ran main water line. Should be tapped next week. Got some exterior lighting installed. Plumbing started.
Sent from my SM-G970U1 using Tapatalk
Comment
-
Cabin build
Looks great! But dang! Put some KO bushings in that panel!! And a ground wire! And the bonding screw!
Sent from my iPhone using Tapatalk ProLast edited by FLASH_OUTDOORS; 04-27-2020, 06:37 AM.
Comment
-
Originally posted by FLASH_OUTDOORS View PostLooks great! But dang! Put some KO bushings in that panel!!
Sent from my iPhone using Tapatalk Pro
Sent from my SM-G970U1 using Tapatalk
Comment
Comment